Custom Research

Central Arizona pH Experiment, U.S.A.
Central Arizona Project manages a 330 mile long system of concrete lined canals, inverted siphons, tunnels, pumping plants and pipe lines which bring water from the Colorado River, on Arizona’s western border, across the state to the canal terminus near Tucson. Quagga mussels have been present in the source waters of the aqueduct (Lake Havasu and Lake Pleasant) for a minimum of two years. In 2008 live veligers, at various stages of development, were observed in plankton samples taken at numerous points of the aqueduct. Despite such observations, very few settled adults were found anywhere in the aqueduct.

Based on the data collected during the 2009 environmental monitoring program, the lack of settled adults in the aqueduct may be due to fortunate combination of environmental factors. This situation may not persist in the future. Central Arizona Project may require a control program which would minimize mussel settlement in the canal and associated structures. One such method of control would be the depression of the pH of the water which is being transported in the canal.

A proof of principle experiment was conducted in 2009, using Lake Ontario water. Veliger rich water was pumped to a flow-through field laboratory. At the laboratory, the pH of the incoming water was adjusted using phosphoric acid to pH 7.3, 7.1 and 6.9. Three replicates of each pH resulted in 9 treatment tanks and three control tanks. The experiment started on June 16, 2009 and it was terminated on November 15, 2009. Adult mortality of almost 40% was recorded at pH 6.9 after 10 weeks of exposure. Analysis of weight/length relationship of adult mussels confirmed that for any given length the mussels were significantly lighter at all three pH levels when compared to the controls. New settlement was essentially prevented at pH of 7.1. Calculations of projected acid use have shown that if sulphuric acid was used, the entire aqueduct could be protected for approximately $10 million in annual chemical costs. There is an opportunity to lower this cost further by treating for only 3 months rather than year around. This would bring the annual cost of chemicals down to $2.5 million.
California Department of Water Resources, U.S.A.
Early in 2008, zebra mussels were confirmed in the San Justo reservoir. The proximity of established mussel populations was seen as increasing the risk of introduction into the State Water Project. RNT Consulting Inc. was asked to examine the South Bay Aqueduct (SBA) portion of the system. The SBA area contains many facilities and structures that are representative of the overall State Water Project system. The objective of the examination was to identify the risks to the facilities should mussels arrive and establish thriving populations.

Several possible control opportunities were identified, some based on extension or modification of existing practices and others on proven technologies. A key recommendation was to continue monitoring programs and to engage in introduction prevention efforts such as public education and outreach. A second key element was to prepare response plans for individual facilities so that budgets were in place and long lead activities were underway when the mussels arrived. Some of the facilities were recommended to be potential candidates for mussel eradication should introduction occur.